CONSENT DECREE MILESTONES
| BASIN |
CSES DUE DATE |
RMAP DUE DATE |
BEGIN CONSTRUCTION |
END CONSTRUCTION |
| LAKEVIEW REHAB |
-- |
-- |
12/15/1998 |
12/14/2001 |
| CBD REHAB |
4/1/1998 |
11/1/1998 |
1/1/2001 |
11/1/2006 |
| GENTILLY REHAB |
4/1/1999 |
11/1/1999 |
1/1/2002 |
12/31/2004 |
| UPTOWN REHAB |
4/1/2000 |
11/1/2000 |
1/1/2003 |
11/1/2006 |
| MID-CITY REHAB |
4/1/2001 |
11/1/2001 |
1/1/2004 |
12/31/2006 |
| LOWER NINTH WARD REHAB |
4/1/2002 |
11/1/2002 |
1/1/2005 |
12/31/2007 |
| CARROLLTON REHAB |
4/1/2003 |
11/1/2003 |
1/1/2006 |
12/31/2008 |
| N.O. EAST REHAB |
4/1/2004 |
11/1/2004 |
1/1/2007 |
12/31/2009 |
| SOUTH SHORE REHAB |
4/1/2005 |
11/1/2005 |
1/1/2008 |
12/31/2010 |
| ALGIERS REHAB |
-- |
-- |
-- |
-- |
| E.B. CAPACITY |
-- |
-- |
-- |
12/31/2010 |
| W.B. CAPACITY |
-- |
-- |
-- |
|
|