> Modified Consent Decree Milestones

BASIN CSES COMPLETION DATE RMAP COMPLETION DATE BEGIN/RESUME CONSTRUCTION END CONSTRUCTION
LAKEVIEW REHAB

--

--

12/15/1998

12/14/2001

FQ/CBD REHAB

4/1/1998

11/1/1998

1/1/2001

12/31/2005

GENTILLY REHAB

4/1/1999

11/1/1999

1/1/2002

12/31/2004

UPTOWN REHAB

4/1/2000

11/1/2000

1/1/2003

12/31/2005

MID-CITY REHAB

4/1/2001

11/1/2001

11/15/2008

7/31/2023

NINTH WARD REHAB

4/1/2002

11/1/2002

11/15/2008

3/31/2018

CARROLLTON REHAB

4/1/2003

11/1/2003

11/15/2008

10/31/2025

N.O. EAST REHAB

4/1/2004

11/1/2004

4/1/2009

10/31/2019

SOUTH SHORE REHAB

4/1/2005

11/1/2005

4/1/2010

10/31/2021


* Algiers Basin is not part of the Consent Decree



> Milestones


> Master Schedule


> Rehabilitation Projects


> Modified Consent Decree Reports


> Grant Quarterly Reports




Contact Us   |   Contractor Login   |   Crew Locations  
  Terms & Conditions/Privacy Policy

© 2010 SSERP, All Rights Reserved.