3801 - Redundant 24 inch Force Main from Pump Station 15 to existing 48-inch Force Main 3802 - Upgrade Pump Station 15 3803 - Replace Pump Station 8 and New 48 inch Discharge Force Main 3819 - New 18-inch Force Main from Pump Station 20 to Pump Station 21 3820 - Upgrade Pump Station 20 3826 - Upgrade Pump Station 16 3829 - New 24" FM along Read Blvd. (Dwyer Rd. to Almonaster Ave.), New 8" FM from PS McCoy to New 24" FM and New 12" FM from PS Willowbrook to existing 16" FM near PS Michoud 3832 - New 6" to 8" FM from SPS Plum Orchard to SPS Dodt and New 12" FM from SPS Wright to SPS Lake Forest 3849 - Gravity Sewer Inter-Connections - East Bank 3859 - East Bank Pump Stations Physical Improvements, No. 2 3864 - New 24-inch Force Main from Pump Station 16 to existing 72-inch Force Main 3866 - East Bank Pump Station Physical Improvements, No. 1 3867 - East Bank Pump Station Physical Improvements, No. 3 3868 - East Bank Pump Station Physical Improvements, No. 4 3869 - East Bank Pump Station Physical Improvements, No. 5 3870 - East Bank Pump Station Physical Improvements, No. 6
3804 - Upgrade Pump Station 5 3805 - New 42" FM from PS 14 to intersection of Dorgenois St. and Toledano St. and New 24" FM from Dorgenois St. and Toledano St. to PS 5 3806 - Upgrade Pump Station 14 3821 - New 24-inch Force Main from Pump Station 22 to Pump Station 21 3822 - New 24-inch Force Main from Pump Station 17 to Pump Station 23 3823 - New 24-inch Force Main from Pump Station 23 to Pump Station K-Mart 3831 - Upgrade Pump Station McCoy 3833 - Upgrade Pump Station Plum Orchard 3850 - East Bank Sewer Treatment Plant Capacity Improvements
3808 - New 54-inch Force Main from the intersection of North Broad Street and Orleans Avenue to Pump Station D 3809 - New 42-inch Force Main from the intersection of Carrollton and Palmyra to Pump Station 8 3810 - New 16-inch Force Main from Pump Station 6 to new 42-inch Force Main at Carrollton Avenue and Palmyra Street 3811 - Upgrade Pump Station 6 3812 - New 42-inch Force Main from Carrollton Avenue at Olive Street to Palmyra 3813 - New 18-inch Force Main from Pump Station 3 to the intersection of Olive Street and Carrollton Avenue 3814 - Upgrade Pump Station 3 3817 - New 18-inch Force Main from Pump Station 1 to the intersection of Carrollton Street and Olive Street 3824 - Upgrade Pump Station 17 3825 - Upgrade Pump Station 23 3838 - New 12-inch Force Main from Pump Station Oak Island to Pump Station Willowbrook 3860 - New Convention Center Pump Station 3861 - New Force Main for Convention Center SPS 3862 - New Medical Center Pump Station 3863 - New Force Main from Medical Center Pump Station to Clara Street Sewer Force Main
3815 - New 42-inch Force Main from Dorgenois Street at Toledano to Olive Street at Carrollton Avenue 3818 - Upgrade Pump Station 1 3827 - New 24-inch Force Main from Pump Station Japonica to existing 72-inch Force Main at Mazant Street 3828 - New Pump Station Japonica
3839 - Redundant 54-inch Force Main from existing 72-inch Force Main near Pump Station A to New 54-inch Force Main near Pump Station 8 3840 - Redundant 24-inch Force Main from Pump Station 22 to Pump Station 17 3842 - Redundant 24-inch Force Main from Pump Station 26 to existing 54-inch Force Main near the East Bank Waste Water Treatment Plant 3843 - Redundant 24-inch Force Main from Pump Station Lamb to existing 30-inch Force Main at the intersection of Dwyer Road and Francis Street 3844 - Redundant 24-inch Force Main from existing 30-inch Force Main near Pump Station Berg to existing 16-inch Force Main near Pump Station Bullard 3845 - Redundant 24-inch Force Main from Pump Station Bullard to Pump Station Wright 3846 - Redundant 54-inch Force Main from New Orleans East Basin to East Bank Waste Water Treatment Plant-Northern Section 3847 - Redundant 54-inch Force Main from New Orleans East Basin to East Bank Waste Water Treatment Plant-Southern Section 3865 - Replacement of Morrison Road Force Main
3851 - Redundant 48-inch Force Main from Pump Station Blair to West Bank Waste Water Treatment Plant 3852 - Pump Station Physical and Structural Improvements-West Bank 3853 - Gravity Sewer Inter-Connections-West Bank 3854 - Redundant 48-inch Force Main from Pump Station Aurora to Pump Station Blair 3855 - Redundant 48-inch Force Main from Pump Station Eton to Pump Station Aurora 3856 - Redundant 42-inch Force Main from Pump Station Huntlee to Pump Station Eton 3857 - Redundant 36-inch Force Main from Pump Station Holiday to Pump Station Huntlee 3858 - Redundant 18-inch Force Main from Pump Station Bridge Plaza to existing 16-inch Force Main